(b) The following activities are a part of project to be scheduled using Critical path method Table 4-1 Activity details
Posted: Thu Apr 28, 2022 10:39 am
(b) The following activities are a part of project to be scheduled using Critical path method Table 4-1 Activity details Activity Preceding activity Time( weeks) A 5 B A 3 с A 7 D C 2 E B.D 4 F D 3 G E,F 11 (i) Draw the network diagram. 5 marks (ii) Calculate slack of all the activities and find the activity that can be delayed highest number of days without affecting the project duration. 5 marks (iii) State the critical path and project duration 3 marks