In the book Advanced Managerial Accounting, Robert P. Mogee discusses monitoring cost variances. A cost variance is the

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

In the book Advanced Managerial Accounting, Robert P. Mogee discusses monitoring cost variances. A cost variance is the

Post by answerhappygod »

In The Book Advanced Managerial Accounting Robert P Mogee Discusses Monitoring Cost Variances A Cost Variance Is The 1
In The Book Advanced Managerial Accounting Robert P Mogee Discusses Monitoring Cost Variances A Cost Variance Is The 1 (63.13 KiB) Viewed 24 times
In The Book Advanced Managerial Accounting Robert P Mogee Discusses Monitoring Cost Variances A Cost Variance Is The 2
In The Book Advanced Managerial Accounting Robert P Mogee Discusses Monitoring Cost Variances A Cost Variance Is The 2 (31.65 KiB) Viewed 24 times
In The Book Advanced Managerial Accounting Robert P Mogee Discusses Monitoring Cost Variances A Cost Variance Is The 3
In The Book Advanced Managerial Accounting Robert P Mogee Discusses Monitoring Cost Variances A Cost Variance Is The 3 (22.24 KiB) Viewed 24 times
In the book Advanced Managerial Accounting, Robert P. Mogee discusses monitoring cost variances. A cost variance is the difference between a budgeted cost and an actual cost. Magee describes the following situation: Michael Bitner hos responsibility for control of two manufacturing processes. Every week he receives a cost variance report for each of the two processes, broken down by labor costs, materials costs, and so on. One of the two processes, which we'll call process A. involves a stable, easily controlled production process with a little fluctuation in variances. Process involves more random events: the equipment is more sensitive and prone to breakdown, the raw material prices fluctuate more, and so on. It seems like I'm spending more of my time with process than with process A" says Michael Bitner. "Yet I know that the probability of an inefficiency developing and the expected costs of inefficiencies are the same for the two processes. It's just the magnitude of random fluctuations that differs between the two, as you can see in the information below." "At present, I investigate variances if they exceed $2,531, regardless of whether it was process A or B. I suspect that such a policy is not the most efficient. I should probably set a higher limit for process B.' The means and standard deviations of the cost varlances of processes A and B when these processes are in control, are as follows: (Round your z value to 2 decimal places and final answers to 4 decimal places.) Mean cost variance (in control) Standard deviation of cont variance (in control) Process A $1 $4,871 Process B $ 1 $10,285 Furthermore, the means and standard deviations of the cost variances of processes A and B when these processes are out of control, are as follows: Mean cont variance (out of control) Standard deviation of cont variance (out of control) Process A 57,190 $4,871 Process o $ 6,455 $10,285 (a) Recall that the current policy is to investigate a cost variance if it exceeds $2,531 for either process. Assume that cost variances are normally distributed and that both Process A and Process B cost variances are in control. Find the probability that a cost variance for Process A will be investigated. Find the probability that a cost variance for Process will be investigated. Which in-control process will be investigated more often
(a) Recall that the current policy is to investigate a cost variance if it exceeds $2,531 for either process. Assume that cost variances are normally distributed and that both Process A and Process B cost variances are in control. Find the probability that a cost variance for Process A will be investigated. Find the probability that a cost variance for Process will be investigated. Which in-control process will be investigated more often Process A Process B is investigated more often (b) Assume that cost variances are normally distributed and that both Process A and Process B cost variances are out of control. Find the probability that a cost variance for Process A will be investigated. Find the probability that a cost variance for Process will be investigated. Which out-of-control process will be investigated more often Process A Process B
(c) If both Processes A and B are almost di ways in control, which process will be investigated more often will be investigated more often (d) Suppose that we wish to reduce the probability that Process will be investigated (when it is in control) to 3015. What cost variance investigation policy should be used? That is, how large a cost variance should trigger an investigation? Using this new policy, what is the probability that an out-of-control cost variance for Process will be investigated? Process B