For this question, use the entire dataset ProjectStatus. Create the classification tree for the variable PS (use entire
Posted: Thu Apr 28, 2022 7:30 am
For this question, use the entire dataset ProjectStatus. Create
the classification tree for the variable PS (use entire dataset),
using rpart package. What is the probability that a project will be
completed on time (2) if the project has a contract days of less
than 137 days, with no additional laborer needed, and with
additional budget of at least 93,000 pesos?
a. 0.70
b. 0.10
c. none of the choices
d. 0.20