1 This person(s) should be involved in the punch list walk thru: (M.C.) A. Owner B. Prime Contactors C. Designer D. All
Posted: Wed Apr 27, 2022 2:58 pm
1 This person(s) should be involved in the punch list walk thru: (M.C.) A. Owner B. Prime Contactors C. Designer D. All of the Above 그 2 The “Close Out” documents typically ends: (M.C.) A. At project completion B. Several Days prior to completion C. Sever days/months after the project completion- D. Depends on the Owner 3 The firms “Close Out” document this used to: (M.C.) - A . Established a templated close out items that are typically are included on the firm's construction project. B ID's the close out sheets related construction project C When the items need to be completed for the scheduled completion date. 4 D All of the above- 4------- The “Close Out” document includes: (M.C.) A Items that need to be completed prior to the project being completed. B The document ID the specific construction project. C The item completion date- D All of the above-