A compacted fill must be placed under all spread footings that have a minimum of 98% relative compaction of the MDD. The
Posted: Wed Apr 27, 2022 2:56 pm
A compacted fill must be placed under all spread footings that
have a minimum of 98% relative compaction of the MDD. The max
dry density is 122.6 pcf. The wet density of 140,8 pcf has a water
content of 21.5% Has the contractor met the required degree for
relative compaction?
have a minimum of 98% relative compaction of the MDD. The max
dry density is 122.6 pcf. The wet density of 140,8 pcf has a water
content of 21.5% Has the contractor met the required degree for
relative compaction?