A borrow site has been located and the soils there have a load factor of 0.88 and a shrinkage factor of 0.94. It require

Posted: Wed Apr 27, 2022 2:52 pm
by answerhappygod
A borrow site has been located and the soils there have a load
factor of 0.88 and a shrinkage factor of 0.94. It requires 2,400
ccy of structural fill. How many bank cubic yards must be removed
from the site to supply the required compacted cubic yards?