Wilton Technologies wishes to use MRP methodology to developing a material requirements plan for the next nine weeks. Wi
Posted: Wed Apr 27, 2022 2:05 pm
Wilton Technologies wishes to use MRP methodology to developing a material requirements plan for the next nine weeks. Williston Technologies has gathered the following information to work with: Bill of Materials: A B с D Current Inventory Records: Part A Leadtime (in weeks) 1 Inventory Currently Lotsize On-hand Lot-for-Lot 50 100 100 25 100 50 400 B С D 2 2 1 Master Production Schedule: -Weeks-
B с D 1 Current Inventory Records: Part A B. С Leadtime (in weeks). 1 2 2 Inventory Currently Lotsize On-hand Lot-for-Lot 50 100 100 25 100 50 400 1 Master Production Schedule: 6 7 -Weeks- 3 4 100 100 8 Part A 9 1 0 2 50 5 250 0 200 0 50 Please use MRP methodology to develop a materials requirement plan for Williston Technologies. Which of the following is true about your plan? I. In Week 9, ending inventory of Part A will be 0. II. In Week 4, ending inventory of Part B will be 50. III. The Week 2 Planned Order Releases for Part C is 250.
B с D 1 Current Inventory Records: Part A B. С Leadtime (in weeks). 1 2 2 Inventory Currently Lotsize On-hand Lot-for-Lot 50 100 100 25 100 50 400 1 Master Production Schedule: 6 7 -Weeks- 3 4 100 100 8 Part A 9 1 0 2 50 5 250 0 200 0 50 Please use MRP methodology to develop a materials requirement plan for Williston Technologies. Which of the following is true about your plan? I. In Week 9, ending inventory of Part A will be 0. II. In Week 4, ending inventory of Part B will be 50. III. The Week 2 Planned Order Releases for Part C is 250.