What are the two key measurement totals at the bottom of a Value Stream Map?

Posted: Mon Aug 28, 2023 12:23 pm
by answerhappygod
Total Inventory and Total People
Total Changeover Time and % Complete & Accurate
Total Takt Time and Total Wait Time
Total Lead Time and Total Process Time