The CEO asks the Developers to add a "very important" item to a Sprint that is in progress.

Posted: Tue Jul 25, 2023 6:31 am
by answerhappygod
What should Developers do?

(choose the best answer)


Inform the Product Owner so they can work with the CEO.
Add the item to the current Sprint and drop an item of equal size.
Add the item to the next Sprint.
Add the item to the current Spring without any adjustments.