How should a Scrum Team deal with non-functional requirements?

Posted: Mon Jul 24, 2023 2:44 pm
by answerhappygod
(choose the best answer)


Manage them during the Integration Sprint prior to the Release Sprint.
Assign them to the lead developers on the team.
Ensure every Increment meets them.
Make suer the release department understands these requirements, but it is not the Scrum Team's responsibility.