The Product Owner is not collaborating with the Developers during the Sprint. What are two valuable actions for a Scrum Master to take?

(choose the best two answers)


Coach the Product owner in the values of Scrum and incremental delivery.
Bring up the problem in the Sprint Retrospective.
Nominate a proxy Product Owner.
Inform the Product Owner's functional manager.
Stop the Sprint, send the Product Owner to a course and restart.