Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started...

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899559
Joined: Mon Aug 02, 2021 8:13 am

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started...

Post by answerhappygod »

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product. The stakeholder is unhappy with the quality of the product. What are two good options for the Scrum Master?

(choose the best two answers)


Coach the Product Owner on how to talk with Developers about this concern.
Wait to bring this up until the Sprint Retrospective.
Explain to the Product Owner that it is up to the Developers to decide on acceptable quality standards.
Encourage the Product Owner to put quality specifications on the Product Backlog and express the stakeholder's concern to the Developers.
Bring the concern to the testers to improve how the Product is verified.
Bring the concern to the testers to improve how the Product is verified.


Several Sprints Into A Project
Several Sprints Into A Project (28.52 KiB) Viewed 224 times
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This question has been solved and has 1 reply.

You must be registered to view answers and replies in this topic. Registration is free.


Register Login
 
Post Reply