Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
Posted: Mon Jul 24, 2023 7:10 am
(choose the best answer)
The Product Owner.
The Project Manager.
The Developers.
The Scrum Team.
The Product Owner.
The Project Manager.
The Developers.
The Scrum Team.