When does a Developer become accountable for the value of a Product Backlog item selected for the Sprint?

Posted: Mon Jul 24, 2023 6:42 am
by answerhappygod
(choose the best answer)


Never. The entire Scrum Team is accountable for creating value every Sprint.
During the Daily Scrum.
Whenever a team member can accommodate more work.
At the Spring Planning Event.