When should a Sprint Goal be created?
Posted: Mon Jul 24, 2023 6:26 am
(choose the best answer)
It should have been created in the previous Sprint during Product Backlog refinement.
During Sprint Planning.
At any time during the Sprint.
A Sprint Goal is not mandatory in Scrum.
It must be established before Spring Planning in order to begin planning.
It should have been created in the previous Sprint during Product Backlog refinement.
During Sprint Planning.
At any time during the Sprint.
A Sprint Goal is not mandatory in Scrum.
It must be established before Spring Planning in order to begin planning.