Which of these may a Scrum Team deliver at the end of a Sprint?

Posted: Mon Jul 24, 2023 6:08 am
by answerhappygod
(choose the best answer)


A valuable, useful increment that meets the Definition of Done.
Failing unit tests, to identify acceptance tests for the next Sprint.
An increment of software with minor known bugs in it.
A single document, if that is what management asked for.