You are the Scrum Master for four Scrum teams working from the same product backlog.

Posted: Sun Jul 23, 2023 2:47 pm
by answerhappygod
You are the scrum master for four scrum teams working from the same product backlog. Several of the Developers come to you complaining that work identified for the upcoming two Sprints will require full-time commitment from a specialist who is external to the teams.

What should the Scrum Master consider in this situation?


(Choose the best two answers)


The desire to maintain a stable velocity.
The ability of the Scrum Teams to produce integrated Increments.
The need to have enough work to keep all Developers busy.
The benefit of Developers figuring out a solution for themselves.