A Physical % complete activity has an original duration of 10, and a remaining duration of10. The actual start is assigned to the activity. Physical % is updated to equal 80%. What is the remaining duration for this activity?
A. 80
B. 10
C. 2
D. 8
A. 80
B. 10
C. 2
D. 8