The Project Manager selects the Update units when costs change on resource assignments option on Calculations tab in Pro
Posted: Sun Jun 11, 2023 4:01 pm
The Project Manager selects the Update units when costs change on resource assignments option on Calculations tab in Project Details. The Budgeted Cost is $2,000 and the Budgeted Units is 80 for the resource on an activity. If the User assigns the activity an Actual Cost of $1,000, what is the Actual Units for the resource?
A. 70
B. 40
C. 60
D. 80
A. 70
B. 40
C. 60
D. 80