An activity has an Original Duration of 10, and a Remaining Duration of 10. The ActualStart is assigned to the activity.
Posted: Sun Jun 11, 2023 4:01 pm
An activity has an Original Duration of 10, and a Remaining Duration of 10. The ActualStart is assigned to the activity. Physical % is updated to equal 80%.What is the Remaining Duration for this activity?
A. 80
B. 10
C. 2
D. 8
A. 80
B. 10
C. 2
D. 8