OSM is executing an order with the process indicated in the diagram. Immediately after the completion of TaskD, a revisi
Posted: Sun Jun 11, 2023 4:00 pm
OSM is executing an order with the process indicated in the diagram. Immediately after the completion of TaskD, a revision is received, which causes only TaskB to be re-evaluated.During the re-execution of TaskB, a significant data element used by TaskA and TaskD is updated in the order. Which task is re-evaluated when the compensation for TaskB completes?
A. TaskA
B. TaskB
C. TaskC
D. TaskD E. TaskE
A. TaskA
B. TaskB
C. TaskC
D. TaskD E. TaskE