Page 1 of 1

More MRP Item Lead Time (LT) 2 Weeks Lot Size On Hand (O/H) Scheduled Receipts (S/R) D(2) 100 100 100 Week 4, 6, & 7 E (

Posted: Wed Apr 27, 2022 1:52 pm
by answerhappygod
More Mrp Item Lead Time Lt 2 Weeks Lot Size On Hand O H Scheduled Receipts S R D 2 100 100 100 Week 4 6 7 E 1
More Mrp Item Lead Time Lt 2 Weeks Lot Size On Hand O H Scheduled Receipts S R D 2 100 100 100 Week 4 6 7 E 1 (129.9 KiB) Viewed 32 times
More MRP Item Lead Time (LT) 2 Weeks Lot Size On Hand (O/H) Scheduled Receipts (S/R) D(2) 100 100 100 Week 4, 6, & 7 E (3) 1 Week 1000 1000 0 D(2) E(3) 1 Item Q. Planned Order Releases 2 50 3 60 4 0 5 50 6 100 7 190 Item: LT: Lot Sizing 1 2 3 4 5 6 7 Gross Requirements Scheduled Receipts Projected on Hand Net Requirements Planned Order Receipts Planned Order Releases Item: LT: Lot Sizing 1 2 3 4 5 6 7 Gross Requirements Scheduled Receipts Projected on Hand Net Requirements Planned Order Receipts Planned Order Releases