If you want the project planned start date to remain the same despite the start date of the earliest task, what property

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899559
Joined: Mon Aug 02, 2021 8:13 am

If you want the project planned start date to remain the same despite the start date of the earliest task, what property

Post by answerhappygod »

If you want the project planned start date to remain the same despite the start date of the earliest task, what property would you disable?

A. Roll up project start date from tasks [com.snc.project.rollup_project_start_date].
B. Max date span into future or past from the current date for the project/project task [com.snc.project.task.check_date_span_years].
C. Retain start on constraint on tasks after adding relations [com.snc.project.allow_start_on_relations].
D. Max duration allowed for a project/project task [com.snc.project.task.max_task_duration].
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This question has been solved and has 1 reply.

You must be registered to view answers and replies in this topic. Registration is free.


Register Login
 
Post Reply