Where is planned cost calculated from when requesting resources from a group and when resource role is specified?
Posted: Thu Apr 06, 2023 1:25 pm
Where is planned cost calculated from when requesting resources from a group and when resource role is specified?
A. The task rate cards.
B. The distribution costs.
C. The hourly rate of the specified role.
D. The CI rate cards.
A. The task rate cards.
B. The distribution costs.
C. The hourly rate of the specified role.
D. The CI rate cards.