What is the default schedule for a project?

Posted: Thu Apr 06, 2023 1:25 pm
by answerhappygod
What is the default schedule for a project?

A. 8-hour workday (from 8 to 12 and 1 to 5).
B. 8-hour workday (from 9 to 12 and 1 to 6).
C. 9-hour workday (from 8 to 12 and from 1 to 5).
D. 8-hour workday (from 9 to 5).