Page 1 of 1

A Development Team member has notified the Scrum Master of a potential data security risk. What action should the Scrum

Posted: Thu Apr 06, 2023 1:25 pm
by answerhappygod
A Development Team member has notified the Scrum Master of a potential data security risk.
What action should the Scrum Master take?

A. Notify the test team.
B. Add a Product Backlog item to address the security issue.
C. Ask the Development Team member to share the issue with the team as soon as possible.
D. Wait until the Sprint Retrospective to add security to the definition of ג€Doneג€.