During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a rel

Posted: Thu Apr 06, 2023 1:25 pm
by answerhappygod
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint.
The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)

A. Stress the value of working software over measured velocity.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
D. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.