During the Sprint Review, the Product Owner decides to release the current Increment to production. The stakeholders sug

Posted: Thu Apr 06, 2023 1:25 pm
by answerhappygod
During the Sprint Review, the Product Owner decides to release the current Increment to production. The stakeholders suggest temporarily delaying the next
Sprint in order to respond more quickly to user feedback after the release. The Product Owner prefers to continue to the next Sprint and make progress towards the next release. Steven, the Scrum Master, begins facilitating the discussion.
What would be two acceptable outcomes of the discussion? (Choose two.)

A. Continue with the Sprints and include the customer feedback in the Product Backlog.
B. Delay the next Sprint to allow the Development Team to work on new customer feedback.
C. Continue with the Sprints but shorten the Sprint time-boxes to allow for shorter feedback loops.
D. Continue with the Sprints but allow the Sprint Goal within the Sprint to change according to the customer feedback.