Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899559
Joined: Mon Aug 02, 2021 8:13 am

After several Sprints, a key stakeholder starts using the product. The stakeholder is surprised by the slow performance

Post by answerhappygod »

After several Sprints, a key stakeholder starts using the product. The stakeholder is surprised by the slow performance and complains to the Product Owner. The
Product Owner comes to the Scrum Master asking for advice.
What is the best action for a Scrum Master to take?

A. Wait until the next Sprint Retrospective as it is the most opportune time to modify the Definition of Done.
B. Bring the concern to the testers in the Development Team and ask them to include performance testing.
C. Explain to the Product Owner that it's up to the Development Team to. decide on acceptable performance standards as they own the Definition of Done.
D. Encourage the Product Owner to bring the performance concerns to the Development Team and work with them on how to improve performance, and ultimately have stronger Definition of Done.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This question has been solved and has 1 reply.

You must be registered to view answers and replies in this topic. Registration is free.


Register Login
 
Post Reply