A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part ti

Posted: Thu Apr 06, 2023 1:25 pm
by answerhappygod
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)

A. Impediments are raised and resolved more slowly.
B. Opportunities to inspect and adapt the Sprint Backlog are reduced.
C. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
D. The Scrum Master loses the ability to update the burndown chart adequately.
E. The Product Owner cannot accurately inspect utilization of the individual team members.