A Development Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain wh
Posted: Thu Apr 06, 2023 1:25 pm
A Development Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what `Done` means. (Choose two.)
A. All work the Development Team is willing to do.
B. Ready for integration.
C. No work left from the definition of ג€Doneג€.
D. Whatever the Product Owner defines as quality.
E. Ready to be released to end users.
A. All work the Development Team is willing to do.
B. Ready for integration.
C. No work left from the definition of ג€Doneג€.
D. Whatever the Product Owner defines as quality.
E. Ready to be released to end users.