What is the basis for approving work results (signing Act of Acceptance) on Project Phase level?
Posted: Thu Apr 06, 2023 1:24 pm
What is the basis for approving work results (signing Act of Acceptance) on Project Phase level?
A. Definition of Done for User Story
B. Definition of Ready for Sprint
C. Scrum of Scrums meeting decision
D. Agreed and met Acceptance Criteria within quality gate
A. Definition of Done for User Story
B. Definition of Ready for Sprint
C. Scrum of Scrums meeting decision
D. Agreed and met Acceptance Criteria within quality gate