Q1. Consider the following project to build a house. Draw the network for the project using the AOA method. What is the

Posted: Wed Apr 27, 2022 1:28 pm
by answerhappygod
Q1 Consider The Following Project To Build A House Draw The Network For The Project Using The Aoa Method What Is The 1
Q1 Consider The Following Project To Build A House Draw The Network For The Project Using The Aoa Method What Is The 1 (164.09 KiB) Viewed 29 times
Q1. Consider the following project to build a house. Draw the network for the project using the AOA method. What is the earliest time you can start to "build house”? When do you have to receive the materials you ordered in order not to delay the project? (7 + 3 + 3 = 13 marks) Time (weeks) 3 Immediate predecessors 2 D 1 Task Description D Design house, obtain financing L Lay foundation O Order and receive materials P Select paint B Build house С F Finish work 1 3 D L,O L,O P B,C Select carpet 1 1