Q1. Consider the following project to build a house. Draw the network for the project using the AOA method. What is the
Posted: Wed Apr 27, 2022 1:28 pm
Q1. Consider the following project to build a house. Draw the network for the project using the AOA method. What is the earliest time you can start to "build house”? When do you have to receive the materials you ordered in order not to delay the project? (7 + 3 + 3 = 13 marks) Time (weeks) 3 Immediate predecessors 2 D 1 Task Description D Design house, obtain financing L Lay foundation O Order and receive materials P Select paint B Build house С F Finish work 1 3 D L,O L,O P B,C Select carpet 1 1