Q2. Draw project network using AON method, filling the ES, EF, LS, LF for each node. What is the critical path(s) and co
Posted: Wed Apr 27, 2022 1:28 pm
Q2. Draw project network using AON method, filling the ES, EF, LS, LF for each node. What is the critical path(s) and completion time of the project? (10 marks) Task A B С D Time (weeks) Immediate predecessors 9 7 A 3 С 6 B 9 B 4 С 6 E,F 5 D 3 G,H E F G H I