Q2. Draw project network using AON method, filling the ES, EF, LS, LF for each node. What is the critical path(s) and co

Posted: Wed Apr 27, 2022 1:28 pm
by answerhappygod
Q2 Draw Project Network Using Aon Method Filling The Es Ef Ls Lf For Each Node What Is The Critical Path S And Co 1
Q2 Draw Project Network Using Aon Method Filling The Es Ef Ls Lf For Each Node What Is The Critical Path S And Co 1 (115.58 KiB) Viewed 27 times
Q2. Draw project network using AON method, filling the ES, EF, LS, LF for each node. What is the critical path(s) and completion time of the project? (10 marks) Task A B С D Time (weeks) Immediate predecessors 9 7 A 3 С 6 B 9 B 4 С 6 E,F 5 D 3 G,H E F G H I