The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
Posted: Wed Mar 15, 2023 5:18 am
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
A. start-to-start (SS)
B. start-to-finish (SF)
C. finish-to-start (FS)
D. finish-to-finish (FF)