When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed

Posted: Wed Mar 15, 2023 5:18 am
by answerhappygod
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

A. Bottom-up
B. Parametric
C. Analogous
D. Three-point