A project requires a component with well-understood specifications. Performance targets are established at the outset, a

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899559
Joined: Mon Aug 02, 2021 8:13 am

A project requires a component with well-understood specifications. Performance targets are established at the outset, a

Post by answerhappygod »

A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:

A. Cost Plus Incentive Fee (CPIF).
B. Fixed Price Incentive Fee (FPIF).
C. Cost Plus Award Fee (CPAF).
D. Fixed Price with Economic Price Adjustment (FP-EPA).
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This question has been solved and has 1 reply.

You must be registered to view answers and replies in this topic. Registration is free.


Register Login
 
Post Reply