In complex projects/ initiating processes should be completed:

Posted: Wed Mar 15, 2023 5:17 am
by answerhappygod
In complex projects/ initiating processes should be completed:

A. Within a work package.
B. In each phase of the project.
C. To estimate schedule constraints.
D. To estimate resource allocations.