The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder i
Posted: Wed Mar 15, 2023 5:17 am
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
A. adaptive
B. reflexive
C. predictive
D. iterative
A. adaptive
B. reflexive
C. predictive
D. iterative