The following is a network diagram for a project. The free float for Activity H is how many days?

Posted: Wed Mar 15, 2023 5:17 am
by answerhappygod
The following is a network diagram for a project.

The free float for Activity H is how many days?
The Following I 1
The Following I 1 (49.01 KiB) Viewed 27 times
A. 4
B. 5
C. 10
D. 11