The following is a network diagram for a project. The free float for Activity H is how many days?
Posted: Wed Mar 15, 2023 5:17 am
The following is a network diagram for a project.
The free float for Activity H is how many days?
A. 4
B. 5
C. 10
D. 11
The free float for Activity H is how many days?
A. 4
B. 5
C. 10
D. 11