The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?
The Following C 1
The Following C 1 (53.34 KiB) Viewed 115 times
A. -2,000
B. 0
C. 1,000
D. 2,000