Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
-
answerhappygod
- Site Admin
- Posts: 899559
- Joined: Mon Aug 02, 2021 8:13 am
Post
by answerhappygod »
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost variance (CV) for Task 6?
- The Following C 1 (53.34 KiB) Viewed 29 times
A. -2,000
B. 0
C. 1,000
D. 2,000