The following is a network diagram for a project. The shortest non-critical path for the project is how many days in dur
Posted: Wed Mar 15, 2023 5:17 am
The following is a network diagram for a project. The shortest non-critical path for the project is how many days in duration?
A. 10
B. 12
C. 14
D. 16
A. 10
B. 12
C. 14
D. 16