The following is a network diagram for a project. The free float for Activity E is how many days?

Posted: Wed Mar 15, 2023 5:17 am
by answerhappygod
The following is a network diagram for a project.

The free float for Activity E is how many days?
The Following I 1
The Following I 1 (53.34 KiB) Viewed 31 times
A. 2
B. 3
C. 5
D. 8