PROJECT MANAGEMENT LAB OVERVIEW
You have been assigned to manage a product launch project from
plan to release. You have completed the project WBS and captured
the duration and predecessors for each task. Your next step is to
determine the project’s end date as well as its critical path to
present to the project's sponsor who is your client. Use Smartsheet
to prepare a Gantt chart and schedule from the Product Launch WBS.
The project’s start date is April 18, 2022, Export the completed
Smartsheet that includes the critical path and project end date as
a pdf document. Please title the project plan and include your
First and Last Name, course (BUS 308 Systems in Organizations), my
name (Professor Lacy), and submission date. Note: The Lab Gantt
chart MUST include the following: Task, Duration, Start, Finish,
Predecessors. and Critical Path. (Points will be loss if ANY of
this information is missing from Lab Submission). Product Launch
Work Breakdown Structure (WBS) Work Stream
Task/Deliverable/Milestone Predecessors Duration Product Launch 1.0
Planning Phase 1.1 Market Requirements Definition 5d 1.2 Business
Case Market Requirements Definition 5d 1.3 Launch Plan Business
Case 5d 1.4 Target Metrics Business Case 4d 2.0 Sales Tools 2.1
Prospect Presentation Market Requirements Definition 5d 2.2 Demo
Prospect Presentation 3d 2.3 Competitive Positioning 2.3.1 FAQ
sheet Prospect Presentation 2d 3.0 Product Marketing 3.1 Pricing
Strategy Market Requirements Definition 7d 3.2 Product Positioning
3.2.1 Define Audience Competitive Positioning 3d 3.2.2 Core
Messaging Competitive Positioning 3d 3.2.3 Executive Approval
Competitive Positioning 2d 4.0 Social 4.1 Define social media
strategy Demo 0.5d 4.2 Schedule social media posts Define social
media strategy 2d 5.0 Product Release 5.1 Alpha Release Launch
Plan, FAQ sheet, Schedule Social media posts ~0 5.2 Beta Release
Alpha Release ~0 5.3 V1 General Availability Beta Release ~0 5.4 R2
Press Event V1 General Availability 2d Deliverable one .pdf file of
the Smartsheet Gantt and Schedule for the Product Launch Product
(must be printed on a single page that includes Project Plan Title,
Task Name, Duration, Start, Finish, and Predecessor.
You have been assigned to manage a product launch project from
plan to release. You have completed the project WBS and captured
the duration and predecessors for each task. Your next step is to
determine the project’s end date as well as its critical path to
present to the project's sponsor who is your client. Use Smartsheet
to prepare a Gantt chart and schedule from the Product Launch WBS.
The project’s start date is April 18, 2022, Export the completed
Smartsheet that includes the critical path and project end date as
a pdf document. Please title the project plan and include your
First and Last Name, course (BUS 308 Systems in Organizations), my
name (Professor Lacy), and submission date. Note: The Lab Gantt
chart MUST include the following: Task, Duration, Start, Finish,
Predecessors. and Critical Path. (Points will be loss if ANY of
this information is missing from Lab Submission). Product Launch
Work Breakdown Structure (WBS) Work Stream
Task/Deliverable/Milestone Predecessors Duration Product Launch 1.0
Planning Phase 1.1 Market Requirements Definition 5d 1.2 Business
Case Market Requirements Definition 5d 1.3 Launch Plan Business
Case 5d 1.4 Target Metrics Business Case 4d 2.0 Sales Tools 2.1
Prospect Presentation Market Requirements Definition 5d 2.2 Demo
Prospect Presentation 3d 2.3 Competitive Positioning 2.3.1 FAQ
sheet Prospect Presentation 2d 3.0 Product Marketing 3.1 Pricing
Strategy Market Requirements Definition 7d 3.2 Product Positioning
3.2.1 Define Audience Competitive Positioning 3d 3.2.2 Core
Messaging Competitive Positioning 3d 3.2.3 Executive Approval
Competitive Positioning 2d 4.0 Social 4.1 Define social media
strategy Demo 0.5d 4.2 Schedule social media posts Define social
media strategy 2d 5.0 Product Release 5.1 Alpha Release Launch
Plan, FAQ sheet, Schedule Social media posts ~0 5.2 Beta Release
Alpha Release ~0 5.3 V1 General Availability Beta Release ~0 5.4 R2
Press Event V1 General Availability 2d Deliverable one .pdf file of
the Smartsheet Gantt and Schedule for the Product Launch Product
(must be printed on a single page that includes Project Plan Title,
Task Name, Duration, Start, Finish, and Predecessor.