Your MRP run detects a shortage of 2000 pieces for a material with an active quota arrangement. Each of your two supplie
Posted: Thu Nov 10, 2022 6:44 am
Your MRP run detects a shortage of 2000 pieces for a material with an active quota arrangement. Each of your two suppliers can only supply 1000 pieces at once.
What must you maintain to have MRP generate a procurement proposal for 1000 pieces for each supplier? (Choose two.)
A. Set a maximum quota quantity in the quota arrangement item for each supplier.
B. Assign a rounding profile in the material master record of the planned material.
C. Set a maximum lot size in the quota arrangement item and activate the 1x checkbox.
D. Assign the indicator for quota splitting to the lot-sizing procedure being used.
What must you maintain to have MRP generate a procurement proposal for 1000 pieces for each supplier? (Choose two.)
A. Set a maximum quota quantity in the quota arrangement item for each supplier.
B. Assign a rounding profile in the material master record of the planned material.
C. Set a maximum lot size in the quota arrangement item and activate the 1x checkbox.
D. Assign the indicator for quota splitting to the lot-sizing procedure being used.