You are using Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development.
You have the following requirements:
✑ All work and progress on individual projects must be reflected in the e-commerce portal development program.
Each group must be able to manage their own tasks.

You need to set up the e-commerce portal development program and its associated projects in Microsoft PPM.
Where should you add resources?
You Are Using M 1
You Are Using M 1 (116 Bytes) Viewed 87 times
A. in the e-commerce portal development program project site
B. in the individual project schedules
C. in Build Team, in the e-commerce portal development program schedule
D. in the individual project sites