How do you ensure that PP/DS planned orders retain the end date and quantity of previously created SNP orders?
Posted: Fri Aug 26, 2022 10:05 am
How do you ensure that PP/DS planned orders retain the end date and quantity of previously created SNP orders?
A. Enter the same value for the SNP production horizon and PP/DS horizon.
B. Activate "determine date and quantity based on SNP order" in Model and Version Management for PP/DS.
C. Use transaction /SAPAPO/SNP2PPDS or interactive function "SNP order conversion".
D. Maintain the SNP production horizon to start at least 1 day before the PP/DS horizon ends.
A. Enter the same value for the SNP production horizon and PP/DS horizon.
B. Activate "determine date and quantity based on SNP order" in Model and Version Management for PP/DS.
C. Use transaction /SAPAPO/SNP2PPDS or interactive function "SNP order conversion".
D. Maintain the SNP production horizon to start at least 1 day before the PP/DS horizon ends.