In the Customizing for requirements planning, a project team notices that the alternativesP1, P2, P3 and P4 are also del

Posted: Fri Aug 26, 2022 10:05 am
by answerhappygod
In the Customizing for requirements planning, a project team notices that the alternativesP1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.What does a firming type define?(Choose two)

A. Handling existing procurement proposals outside the planning time fence.
B. Handling existing procurement proposals within a planning time fence.
C. Handling new requirements within the planning time fence.
D. Handling new procurement proposals that need to be created due to new requirements within the planning time fence.