The client has a requirement to setup a reconciliation schedule against a given service that will run only on Monday. We
Posted: Fri Aug 26, 2022 9:58 am
The client has a requirement to setup a reconciliation schedule against a given service that will run only on Monday. Wednesday, and Friday at 8:00 am.How many schedules will need to be setup for the service in order to meet the requirement?
A. It is not possible to meet the requirement.
B. Three schedules will be needed.
C. Two schedules will needed.
D. One schedule will needed.
A. It is not possible to meet the requirement.
B. Three schedules will be needed.
C. Two schedules will needed.
D. One schedule will needed.